Martinez Junior High - Locker Rooms Renovation
PROJECT UPDATES:
August 14, 2019
First day of school at MUSD. The new lockers and flooring are complete. Benches will be installed soon to the specifications of the MJHS athletic department staff. Construction team has located compatible evaporative cooling systems and they have been ordered. Installation is scheduled tentatively for mid-September.
June 10, 2019
Demolition begins on the locker rooms as soon as school is out. Construction team is doing research on cooling units that may be installed in the locker rooms.
April 29, 2019
Bond team meets with MJHS athletic department to review final design plans and timeframe for locker room renovation project.
March 25, 2019
MUSD School Board approves revised budget ($2,000,000 for Locker Rooms and Maker Space projects) and directs District staff to move forward on the MJHS locker room project.
January 30, 2019
Bond team meets with MJHS athletic department and admin to discuss needs and wants for the locker room renovations .
Approved by Board of Education: March 25, 2019
Contractor: R.A. Jones
Project Manager: Jon Novero, RGM & Associates
Project Budget: $2,000,000.00 (combined with MJHS Maker Space project)
Expensed-to-date: $287,972.36*
Associated Bond Language:
"Modernize, renovate, rehabilitate, re-configure, expand, upgrade and/or equip locker rooms, gymnasiums, pools, athletic stadiums and related athletic facilities."